| Fuel
Wood chip and Salix.
Boiler
Danstoker 3.5 MW FVB – installed 2002.
Soot-blower
The boiler was delivered with a competeting
soot-blowing system at the top of the boiler.
- 9 pcs. valves on 1st stroke countercurrent
- 5 pcs. valves on 2nd stroke wake
- 7 pcs. valves on 3rd stroke countercurrent.
Efficiency
Mechanical cleaning seems to be necessary several times per month – the pipes are not kept clean.
Initiative
It was decided to replace the soot-blowing system on the 1st stroke.
AEROVIT soot-blowers on a new boiler door were delivered February 2003. |
|
| AEROVIT on the first stroke |
|
Result
Mechanical cleaning only necessary twice a year.
The pipes in 1st stroke are now kept clean.
The pipes in 2nd stroke are now kept fairly clean.
The pipes in 3rd stroke are not kept clean.
Future
If the remaining soot-blowing system is replaced with AEROVIT valves, it is to be expected that there will be a need for mechanical cleaning only once every 2 or 3 year.
|